Mumbai Metro advances key line milestones as girder work reaches Juhu Circle

The Mumbai Metropolitan Region Development Authority is pushing forward with girder installations on Line 2B while advancing civil work across Line 4 and Line 6.

By The India Decade

The Mumbai Metropolitan Region Development Authority (MMRDA) is completing the final girder installations at Juhu Circle on Metro Line 2B, marking a major structural milestone towards opening the 7.53-kilometre Andheri West to Saraswat Nagar corridor by March 2027.

Engineers are placing the last three of 20 massive concrete I-girders near the ESIC Metro Station. Each beam spans 33 metres and weighs 115 metric tonnes. To minimise local disruption along the narrow Gulmohar Road section, MMRDA and contractor J Kumar Infraprojects scheduled heavy crane operations during night-time closures.

Overall civil and systems progress on Line 2B has reached 75 per cent. Following the opening of the initial stretch in 2027, the remaining 10.03-kilometre section extending from Saraswat Nagar to Chembur is targeted for completion in 2028.

Progress across key Mumbai Metro corridors

Beyond Line 2B, MMRDA has recorded substantial execution figures across other primary corridors, including Green Line 4 and Pink Line 6, which together represent an investment of ₹21,265 crore across 43 stations.

Metro CorridorRoute StretchCivil ProgressOperational Target
Line 2B (Phase 1)Andheri West to Saraswat Nagar75% completeMarch 2027
Line 2B (Phase 2)Saraswat Nagar to ChemburIn progress2028
Green Line 4Wadala to KasaradavaliOver 90% civil work doneTrial runs under way (4/4A)
Pink Line 6Lokhandwala to KanjurmargKey site clearances securedIn progress

On Green Line 4, structural progress has passed critical benchmarks: pier construction stands at 95 per cent, U-girder placement at 94 per cent, and deck-slab work at 92 per cent. Transit authorities have already commenced trial runs on the northern Line 4/4A section after resolving land acquisition for the Laxmi Nagar site in Vikhroli East, acquired for ₹164.31 crore.

Similarly, key legal hurdles facing Pink Line 6 have been overcome. The Supreme Court dismissed appeals regarding the 15-hectare depot site in Kanjurmarg, paving the way for uninterrupted depot construction and full system integration.

Once fully commissioned, Green Line 4 is projected to carry approximately 12.13 lakh passengers daily by 2031, while Pink Line 6 is expected to serve 7.69 lakh commuters each day, dramatically easing traffic congestion across the Mumbai metropolitan area.

Key numbers

WhatFigureSource
Line 2B overall progress75%MMRDA
Girder weight at Juhu Circle115 metric tonnesMMRDA
Combined cost of Line 4 and Line 6₹21,265 croreMMRDA
Line 4 daily commuters by 203112.13 lakhMMRDA
Laxmi Nagar land acquisition cost₹164.31 croreMMRDA

In this story

NameRole in the story
MMRDAThe state authority overseeing construction and execution of the Mumbai Metro network.
Mumbai MetroThe rapid transit system under active construction across the metropolitan area.