Mumbai Metro advances key line milestones as girder work reaches Juhu Circle
The Mumbai Metropolitan Region Development Authority is pushing forward with girder installations on Line 2B while advancing civil work across Line 4 and Line 6.
The Mumbai Metropolitan Region Development Authority (MMRDA) is completing the final girder installations at Juhu Circle on Metro Line 2B, marking a major structural milestone towards opening the 7.53-kilometre Andheri West to Saraswat Nagar corridor by March 2027.
Engineers are placing the last three of 20 massive concrete I-girders near the ESIC Metro Station. Each beam spans 33 metres and weighs 115 metric tonnes. To minimise local disruption along the narrow Gulmohar Road section, MMRDA and contractor J Kumar Infraprojects scheduled heavy crane operations during night-time closures.
Overall civil and systems progress on Line 2B has reached 75 per cent. Following the opening of the initial stretch in 2027, the remaining 10.03-kilometre section extending from Saraswat Nagar to Chembur is targeted for completion in 2028.
Progress across key Mumbai Metro corridors
Beyond Line 2B, MMRDA has recorded substantial execution figures across other primary corridors, including Green Line 4 and Pink Line 6, which together represent an investment of ₹21,265 crore across 43 stations.
| Metro Corridor | Route Stretch | Civil Progress | Operational Target |
|---|---|---|---|
| Line 2B (Phase 1) | Andheri West to Saraswat Nagar | 75% complete | March 2027 |
| Line 2B (Phase 2) | Saraswat Nagar to Chembur | In progress | 2028 |
| Green Line 4 | Wadala to Kasaradavali | Over 90% civil work done | Trial runs under way (4/4A) |
| Pink Line 6 | Lokhandwala to Kanjurmarg | Key site clearances secured | In progress |
On Green Line 4, structural progress has passed critical benchmarks: pier construction stands at 95 per cent, U-girder placement at 94 per cent, and deck-slab work at 92 per cent. Transit authorities have already commenced trial runs on the northern Line 4/4A section after resolving land acquisition for the Laxmi Nagar site in Vikhroli East, acquired for ₹164.31 crore.
Similarly, key legal hurdles facing Pink Line 6 have been overcome. The Supreme Court dismissed appeals regarding the 15-hectare depot site in Kanjurmarg, paving the way for uninterrupted depot construction and full system integration.
Once fully commissioned, Green Line 4 is projected to carry approximately 12.13 lakh passengers daily by 2031, while Pink Line 6 is expected to serve 7.69 lakh commuters each day, dramatically easing traffic congestion across the Mumbai metropolitan area.
Key numbers
| What | Figure | Source |
|---|---|---|
| Line 2B overall progress | 75% | MMRDA |
| Girder weight at Juhu Circle | 115 metric tonnes | MMRDA |
| Combined cost of Line 4 and Line 6 | ₹21,265 crore | MMRDA |
| Line 4 daily commuters by 2031 | 12.13 lakh | MMRDA |
| Laxmi Nagar land acquisition cost | ₹164.31 crore | MMRDA |
In this story
| Name | Role in the story |
|---|---|
| MMRDA | The state authority overseeing construction and execution of the Mumbai Metro network. |
| Mumbai Metro | The rapid transit system under active construction across the metropolitan area. |