TAPI gas pipeline advances as Turkmenistan targets 2026 completion for Afghan section
The 153-kilometre Serhetabat–Herat stretch marks key progress on the cross-border energy corridor linking Central Asia with South Asia.
Turkmenistan expects to complete the 153-kilometre Serhetabat–Herat section of the Turkmenistan–Afghanistan–Pakistan–India (TAPI) natural gas pipeline by the end of 2026, setting the stage for initial gas deliveries to western Afghanistan in early 2027.
Work on the ground is moving steadily. Approximately 124 kilometres of the Afghan stretch have already been welded and laid, according to Turkmen officials. Remaining tasks include completing the final pipe installation, backfilling, building access crossings, and constructing a dedicated gas metering station. Afghan media reports estimate the development cost of this Herat section at around $600 million.
TAPI pipeline key figures
| Measure | Figure |
|---|---|
| Total pipeline length | 1,800 km |
| Serhetabat–Herat section length | 153 km |
| Completed pipe welding | 124 km |
| Annual transportation capacity | 33 billion bcm |
| Total estimated project cost | $10 billion |
| Herat section cost | $600 million |
The full $10-billion cross-border network is designed to transport 33 billion cubic metres (bcm) of natural gas annually across its 1,800-kilometre route. It connects Turkmenistan’s extensive reserves with energy-demanding economies in South Asia. India and Pakistan collectively import between 45 and 50 bcm of natural gas each year, making regional pipeline integration a long-term strategic goal for subcontinental energy security.
Under initial commercial agreements, Afghanistan is slated to purchase approximately 500 million cubic metres of gas per year for Herat. Muhammetmyrat Amanov, head of the Turkmen state company steering the pipeline, noted that establishing early operations and revenue in Herat is intended to bolster confidence among potential international financiers. International institutions such as the Asian Development Bank and the Islamic Development Bank have previously been identified as potential funding partners, though formal commitments remain subject to standard due diligence and regional political stability.
For Turkmenistan, the project serves as a vital avenue to diversify exports beyond its main buyer, China. For South Asia, the progress on TAPI highlights the ongoing momentum behind regional infrastructure delivery, economic connectivity, and extended neighbourhood integration.
Key numbers
| What | Figure | Source |
|---|---|---|
| Serhetabat-Herat section length | 153 km | Turkmen state pipeline authority |
| Afghan section length welded and laid | 124 km | Turkmen state pipeline authority |
| Herat section estimated cost | $600 million | Afghan media reports |
| Total TAPI pipeline length | 1,800 km | TAPI Pipeline Company Limited |
| Total estimated project cost | $10 billion | TAPI Pipeline Company Limited |
| Annual pipeline capacity | 33 billion cubic metres | TAPI Pipeline Company Limited |
In this story
| Name | Role in the story |
|---|---|
| Turkmenistan | Initiating nation advancing the pipeline construction. |
| Afghanistan | Transit country hosting the Serhetabat-Herat pipeline section. |
| India | Terminal market country for the TAPI pipeline network. |
| Pakistan | Transit and buyer nation along the TAPI pipeline route. |
| Herat | Afghan city targeted for initial gas delivery in early 2027. |