TAPI gas pipeline advances as Turkmenistan targets 2026 completion for Afghan section

The 153-kilometre Serhetabat–Herat stretch marks key progress on the cross-border energy corridor linking Central Asia with South Asia.

By The India Decade

Turkmenistan expects to complete the 153-kilometre Serhetabat–Herat section of the Turkmenistan–Afghanistan–Pakistan–India (TAPI) natural gas pipeline by the end of 2026, setting the stage for initial gas deliveries to western Afghanistan in early 2027.

Work on the ground is moving steadily. Approximately 124 kilometres of the Afghan stretch have already been welded and laid, according to Turkmen officials. Remaining tasks include completing the final pipe installation, backfilling, building access crossings, and constructing a dedicated gas metering station. Afghan media reports estimate the development cost of this Herat section at around $600 million.

TAPI pipeline key figures

MeasureFigure
Total pipeline length1,800 km
Serhetabat–Herat section length153 km
Completed pipe welding124 km
Annual transportation capacity33 billion bcm
Total estimated project cost$10 billion
Herat section cost$600 million

The full $10-billion cross-border network is designed to transport 33 billion cubic metres (bcm) of natural gas annually across its 1,800-kilometre route. It connects Turkmenistan’s extensive reserves with energy-demanding economies in South Asia. India and Pakistan collectively import between 45 and 50 bcm of natural gas each year, making regional pipeline integration a long-term strategic goal for subcontinental energy security.

Under initial commercial agreements, Afghanistan is slated to purchase approximately 500 million cubic metres of gas per year for Herat. Muhammetmyrat Amanov, head of the Turkmen state company steering the pipeline, noted that establishing early operations and revenue in Herat is intended to bolster confidence among potential international financiers. International institutions such as the Asian Development Bank and the Islamic Development Bank have previously been identified as potential funding partners, though formal commitments remain subject to standard due diligence and regional political stability.

For Turkmenistan, the project serves as a vital avenue to diversify exports beyond its main buyer, China. For South Asia, the progress on TAPI highlights the ongoing momentum behind regional infrastructure delivery, economic connectivity, and extended neighbourhood integration.

Key numbers

WhatFigureSource
Serhetabat-Herat section length153 kmTurkmen state pipeline authority
Afghan section length welded and laid124 kmTurkmen state pipeline authority
Herat section estimated cost$600 millionAfghan media reports
Total TAPI pipeline length1,800 kmTAPI Pipeline Company Limited
Total estimated project cost$10 billionTAPI Pipeline Company Limited
Annual pipeline capacity33 billion cubic metresTAPI Pipeline Company Limited

In this story

NameRole in the story
TurkmenistanInitiating nation advancing the pipeline construction.
AfghanistanTransit country hosting the Serhetabat-Herat pipeline section.
IndiaTerminal market country for the TAPI pipeline network.
PakistanTransit and buyer nation along the TAPI pipeline route.
HeratAfghan city targeted for initial gas delivery in early 2027.